|
Timeline
A
check of the minutes taken at the Heath Residents Association
meeting in September 2000 show that this was the earliest mention
of restoring the Pinfold. There was illegal tipping taking place
and it was felt that the council should be contacted with a view
to removing tyres and other rubbish.
In
spring of 2001 the pinfold had been cleared of the tyres and other
rubbish by the local council and it was further cleared by the
residents of all the smaller rubbish while the trees, grass, gorse
and blackberry vines which in summer overgrows the area were still
dormant from the winter period.
The
project did not gain much momentum at this time and it wasn’t
until later that residents volunteered to oversee the restoration
and started looking at the Pinfold in more detail.
November
2001.
The
pinfold was quite an overgrown area with quite substantial maple
trees having grown around and within the pinfold walls.
The Countryside Service under the guidance of David Mee
were contacted with a view to having the trees cut down and
removed.
April
2002.
No
further news was reported to the residents at this meeting of the
residents association.
February
2003.
Local
residents with the onset of winter offered their support on a
stone gathering working party on the 22nd February to
collect random stone strewn about the pinfold area; this was
collected when the grass and gorse had died back for the winter
and an initial clearing of the site took place, the tree stumps
were also removed from the pinfold at this time.
Two
piles of stone were collected, one in the centre of the Pinfold
the other to the left of the gate posts.
At
this time it was also decided to contact local stonemasons to
obtain a price for the restoration of the Pinfold.
October
2003.
Work
began in earnest to research various options to acquire external
funding for the project and the Local Heritage Initiative was
initially approached with positive feedback.
November
2003.
One
quote had been obtained to restore the pinfold but a second was
required for LHI purposes.
January
2004.
Still
awaiting a second costing to restore the pinfold.
Between
January and September research, permissions and other work
required for the successful application to be made was undertaken.
September
2004.
A
draught application was made to the Local Heritage Initiative
which is a partnership between the Heritage Lottery Fund,
Nationwide Building Society and The Countryside Agency to fund the
restoration project.
November
2004.
Draught
application submitted to LHI who required further information
regarding certain aspects of the project.
January
2005.
A
water colour painting had been obtained from a local resident
depicting what the pinfold looked like in its prime.
This has been recorded digitally and with the existing
archeology of the pinfold will form the basis of the restoration
to restore the pinfold to its former glory.

A drawing of Heath Pinfold by the late Mr Stanley Morley.
April
2005.
Progress
was still ongoing with the application.
May
2005.
Work
started by Colin Daley to record the progress of the pinfold
restoration and the creation of a web page to promulgate the
project.
June
2005.
2nd
June 2005, approval of funding from LHI.
Negotiations with the stonemason Kim Naylor to formulate a
timetable of restoration.
August
2005.
Site
preparation in consultation with Kim Naylor to remove invasive
vegetation and to make the site secure.
October
2005.
Mid
October Work began formally on the project with local residents
assisting Kim Naylor in conjunction with Colin Daley (Vice Chair
Heath Residents Association) who was now steering the project.

The Pinfold just prior to the renovation taking place.
The
renovation project was designed to incorporate a skill transfer
with three weekends throughout the project allocated to this end.
These were well attended by local residents and additional
assistance was given throughout the months by residents with a
view to learning more about dry stone walling and to be more
involved in the project.
Commemorative
date Stone ordered.
November
2005.
The
bulk of the renovation is complete with the pinfold restored to
its original height and dimensions, however difficulty in sourcing
appropriate coping stones to finish the project are encountered.
This is causing a delay in the landscaping and fencing of
the pinfold.

The pinfold after initial landscaping is awaiting coping
stones to finish the walls.
December
2005.
Coping
stones sourced but poor weather and existing commitments on behalf
of Kim Naylor are delaying completion.
February
2006.
Back
to top |